ticker: AEE
company: AEE
filing_type: 10-K
year_current: 2024
year_prior: 2023
risks_added: 1
risks_removed: 0
risks_modified: 7
risks_unchanged: 13
source: SEC EDGAR
url: https://riskdiff.com/aee/2024-vs-2023/
markdown_url: https://riskdiff.com/aee/2024-vs-2023/index.md
generated: 2026-06-01
---

# AEE: 10-K Risk Factor Changes 2024 vs 2023

> Source: U.S. Securities and Exchange Commission (EDGAR)  
> Generated: 2026-06-01  
> All data extracted directly from official filings. No hallucinated content.

## Summary

| Status | Count |
|--------|-------|
| New risks added | 1 |
| Risks removed | 0 |
| Risks modified | 7 |
| Unchanged | 13 |

---

## New in Current Filing: Beginning in 2024 through at least 2027, electric distribution rates for Ameren Illinois are established through an MYRP, which are subject to ongoing regulatory and judicial proceedings and associated risks, and are subject to a reconciliation cap. Additionally, Ameren Illinois is subject to certain performance metrics that if not achieved would result in a reduction to the company's allowed ROE.

The CEJA resulted in changes to the regulatory framework applicable to Ameren Illinois' electric distribution business by giving Ameren Illinois the option to file an MYRP with the ICC or establish future rates through a traditional regulatory rate review, among other things. An MYRP establishes rates for a four-year period, and Ameren Illinois has the option to file for an MYRP every four years. Ameren Illinois elected to file an MYRP for rates effective in 2024 through 2027. Under the MYRP, Ameren Illinois will reconcile its actual revenue requirement, as adjusted for certain cost variations, to ICC-approved electric distribution service rates on an annual basis, subject to a reconciliation cap. The reconciliation cap limits the annual adjustment to 105% of the annual revenue requirement approved by the ICC. Certain variations from forecasted costs are excluded from the reconciliation cap, including those associated with major storms; new business and facility relocations; changes in the timing of certain expenditures or investments into or out of the applicable calendar year; and changes in interest rates, income taxes, taxes other than income taxes, pension and other post-retirement benefits costs, and amortization of certain assets. The reconciliation cap also excludes costs recovered outside of base rates through riders. Ameren Illinois' existing riders remain effective and electric distribution service revenues continue to be decoupled from sales volumes under the MYRP. The actual revenue requirement for a particular year incorporates Ameren Illinois' year-end rate base and actual capital structure for such year, provided that the resulting revenue requirement does not exceed the 105% reconciliation cap and the common equity ratio in such capital structure may not exceed that approved by the ICC in the MYRP. In addition, the ICC determines the ROE applicable to each year of the four-year period. Economic conditions could result in the annual predetermined ROE becoming inadequate over the four-year period. In December 2023, the ICC issued an order in Ameren Illinois' MYRP proceeding, approving revenue requirements for electric distribution service for 2024, 2025, 2026, and 2027 of $1,162 million, $1,210 million, $1,242 million, and $1,255 million, respectively. These revenue requirements were established under an alternative methodology which used Ameren Illinois' previously approved 2022 year-end rate base since the order rejected the Grid Plan that was filed by Ameren Illinois as a part of the MYRP proceeding. The ICC concluded that the proposed Grid Plan did not meet certain statutory requirements and directed Ameren Illinois to file a revised Grid Plan within three months. Ameren Illinois expects to file a revised Grid Plan with the ICC in March 2024, and also expects to file a request to update the associated MYRP revenue requirements for 2024 through 2027 in the first half of 2024. The 2022 year-end rate base will remain in effect through 2027, unless subsequently changed by the ICC in the rehearing discussed below or if approval of a revised Grid Plan results in an update of each year's revenue requirement. In January 2024, Ameren Illinois filed a request for rehearing of the ICC's December 2023 order. The filing contended that the use of the 2022 year-end rate base for each year of the MYRP, until a revised Grid Plan is approved, is unlawful and not in compliance with the CEJA. In addition, the filing requested the ICC revise the order to include an allowed ROE of at least 9.82% for each year of the MYRP and include a base level of investments to maintain grid reliability in each year of the MYRP, among other things. In January 2024, the ICC partially denied Ameren Illinois' rehearing request by denying Ameren Illinois' request regarding the allowed ROE, and granting Ameren Illinois' request to consider whether it is appropriate to use the 2022 year-end rate base for each year of the MYRP and to include a base level of investments to maintain grid reliability in each year of the MYRP. Additionally, the scope of the rehearing will include a review of certain operations and maintenance expenses in each year of the MYRP. In February 2024, Ameren Illinois filed its request in the rehearing proceeding, which proposed updated revenue requirements of $1,214 million, $1,300 million, $1,371 million, and $1,420 million, for 2024, 2025, 2026, and 2027, respectively. An ICC decision in this rehearing is expected by late June 2024. Also, in January 2024, Ameren Illinois filed an appeal of the December 2023 ICC order and the partial denial of Ameren Illinois' request for rehearing to the Illinois Appellate Court for the Fifth Judicial District. The court is under no deadline to address the appeal. Ameren Illinois cannot predict the ultimate outcome of the revised Grid Plan filing, its request to update the associated MYRP revenue requirements for 2024 through 2027, the rehearing proceeding, or the appeal to the Illinois Appellate Court for the Fifth Judicial District. Failure to limit capital expenditures and operation and maintenance expenses to amounts 21 21 21 Table of Contents Table of Contents to which maintain revenue requirements under the reconciliation cap limit would adversely affect Ameren's and Ameren Illinois' results of operations, financial position, and liquidity. Ameren Illinois' electric distribution service business is also subject to performance metrics. Failure to achieve the metrics would result in a reduction in the company's allowed ROE calculated under the MYRP. In 2022, the ICC issued an order approving total ROE incentives and penalties of 24 basis points under the MYRP, allocated among seven performance metrics. These performance metrics include improvements in service reliability in both the frequency and duration of outages, a reduction in peak loads, an increased percentage of spend with diverse suppliers, a reduction in disconnections for certain customers, and improved timeliness in response to customer requests for interconnection of distributed energy resources. These performance metrics apply annually from 2024 through 2027 under the MYRP, and the impact of any incentives and penalties will be excluded from the reconciliation cap described above. In addition, the allowed ROE on energy-efficiency investments can be increased or decreased up to 200 basis points, depending on the achievement of annual energy savings goals. Any adjustments to the allowed ROE for energy-efficiency investments will depend on annual performance for a historical period relative to energy savings goals.

---

## Modified: We are subject to various environmental and permitting laws. Significant capital expenditures may be required to achieve and to maintain compliance with these environmental laws. Failure to comply with these laws could result in the closing of facilities, alterations to the manner in which these facilities operate, increased operating costs, delays and increased costs of building new facilities, and exposure to fines and liabilities.

**Key changes:**

- Reworded sentence: "Our electric generation, transmission, and distribution and natural gas distribution and storage operations must comply with a variety of statutes and regulations relating to the protection of the environment and human health and safety, including permitting programs implemented by federal, state, and local authorities."
- Reworded sentence: "Complex and lengthy processes are required to obtain and renew approvals, permits, and licenses for new, existing, or modified energy-related facilities."
- Reworded sentence: "Further, we are subject to risks from changing or conflicting interpretations of existing laws, modifications to existing laws, new laws, new or modified permit terms, and enforcement of environmental laws and permits by federal, state, and local authorities."
- Reworded sentence: "Additionally, individuals and non-governmental organizations may seek to enforce environmental laws against us, allege injury from exposure to hazardous materials, allege a failure to comply with environmental laws, seek to compel remediation of environmental contamination, or seek to recover damages resulting from purported contamination."
- Reworded sentence: "As of December 31, 2023, Ameren Missouri's coal-fired energy centers represented 8% and 16% of Ameren's and Ameren Missouri's rate base, respectively."

**Prior (2023):**

Our electric generation, transmission, and distribution and natural gas distribution and storage operations must comply with a variety of statutes and regulations relating to the protection of the environment and human health and safety including permitting programs implemented by federal, state, and local authorities. Such environmental laws address air emissions; discharges to water bodies; the storage, handling and disposal of hazardous substances and waste materials; siting and land use requirements; and potential ecological impacts. Complex and lengthy processes are required to obtain and renew approvals, permits, and licenses for new, existing, or modified facilities. Additionally, the use and handling of various chemicals or hazardous materials require release prevention plans and emergency response procedures. Further, we are subject to risks from changing or conflicting interpretations of existing laws, modification to existing laws, new laws, and new or modified permit terms. We are also subject to liability under environmental laws that address the remediation of environmental contamination on property currently or formerly owned by us or by our predecessors, as well as property contaminated by hazardous substances that we generated. Such properties include MGP sites, substations, and third-party sites, such as landfills. Additionally, private individuals may seek to enforce environmental laws against us. They could allege injury from exposure to hazardous materials, allege a failure to comply with environmental laws, seek to compel remediation of environmental contamination, or seek to recover damages resulting from that contamination. Environmental regulations have a significant impact on the electric utility industry and compliance with these regulations could be costly for Ameren Missouri, which operates coal-fired power plants. As of December 31, 2022, Ameren Missouri's coal-fired energy centers represented 9% and 17% of Ameren's and Ameren Missouri's rate base, respectively. Regulations under the Clean Air Act that apply to the electric utility industry include the NSPS, the CSAPR, the MATS, and the National Ambient Air Quality Standards, which are subject to periodic review for certain pollutants. Collectively, these regulations cover a variety of pollutants, such as SO2, particulate matter, NOx, mercury, toxic metals, and acid gases, and CO2 emissions from new power plants. Regulations implementing the Clean Water Act govern both intake and discharges of water, as well as evaluation of the ecological and biological impact of our operations and could require modifications to water intake structures or more stringent limitations on wastewater discharges. Depending upon the scope of modifications ultimately required by state regulators, capital expenditures associated with these modifications could be significant. The management and disposal of coal ash is regulated under the Resource Conservation and Recovery Act and the CCR Rule, which require the closure of our surface impoundments at Ameren Missouri's coal-fired energy centers. The individual or combined effects of compliance with existing and new environmental regulations could result in significant capital expenditures, increased operating costs, or the closure or alteration of operations at some of Ameren Missouri's energy centers. In January 2011, the United States Department of Justice, on behalf of the EPA, filed a complaint against Ameren Missouri in the United States District Court for the Eastern District of Missouri alleging that projects performed in 2007 and 2010 at the coal-fired Rush Island Energy Center violated provisions of the Clean Air Act and Missouri law. In January 2017, the district court issued a liability ruling against Ameren Missouri and, in September 2019, entered a remedy order. That remedy order included a requirement to install a flue gas desulfurization system at the Rush Island Energy Center, which was upheld through an appeals process by the United States Court of Appeals for the Eighth Circuit in the fourth quarter of 2021. Based on its assessment of available legal, operational and regulatory alternatives, Ameren Missouri filed a motion in December 2021 with the district court to modify the remedy order to allow the retirement of the Rush Island Energy Center in advance of its previously expected useful life in lieu of installing a flue gas desulfurization system. The March 31, 2024 compliance date contained in the district court's September 2019 remedy order remains in effect unless extended by the district court. In July 2022, in response to an Ameren Missouri request for a final, binding reliability assessment, the MISO designated the Rush Island Energy Center as a system support resource and concluded that certain mitigation measures, including transmission upgrades, should occur before the energy center is retired. The transmission upgrade projects have been approved by the MISO, and design and procurement activities necessary to complete the upgrades are underway. Ameren Missouri expects to complete the upgrades by mid-2025. In October 2022, the FERC approved a system support resource agreement, which became effective retroactively as of September 1, 2022. The agreement details the manner of continued operation for a system support resource that results in operating during peak demand times and emergencies. The system support resource designation and the related agreement are subject to annual renewal and revision. In September 2022, the Rush Island Energy Center began operating consistent with the system support resource agreement. In addition, in October 2022, the FERC established hearing and settlement procedures in response to an August 2022 request from Ameren Missouri for recovery of non-energy costs under the related MISO tariff. The FERC is under no deadline to issue an order related to this proceeding. Revenues and costs under the MISO tariff are expected to be included in the FAC. The district court has the authority to determine the 23 23 23 Table of Contents Table of Contents retirement date and operating parameters for the Rush Island Energy Center and is not bound by the MISO determination of the Rush Island Energy Center as a system support resource or the FERC's approval. The district court is under no deadline to issue a ruling modifying the remedy order. Related to this matter, in February 2022, the MoPSC issued an order directing the MoPSC staff to review Ameren Missouri's planned accelerated retirement of the Rush Island Energy Center, including potential impacts on the reliability and cost of Ameren Missouri's service to its customers; Ameren Missouri's plans to mitigate the customer impacts of the accelerated retirement; and the prudence of Ameren Missouri's actions and decisions with regard to the Rush Island Energy Center, among other things. In April 2022, the MoPSC staff filed an initial report with the MoPSC in which the staff concluded early retirement of the Rush Island Energy Center may cause reliability concerns. The MoPSC staff is under no deadline to complete this review. Ameren Missouri expects to seek approval from the MoPSC to finance the costs associated with the retirement, including the remaining unrecovered net plant balance associated with the facility, through the issuance of securitized utility tariff bonds pursuant to Missouri's securitization statute. If the remaining unrecovered net plant balance for the Rush Island Energy Center and an associated return are not recoverable through base rates or other regulatory mechanisms, Ameren Missouri would recognize an abandonment loss equal to the difference between the remaining net book value of the asset and the present value of the expected future cash flows. As of December 31, 2022, the Rush Island Energy Center had a net plant balance of approximately $0.6 billion and a rate base of approximately $0.4 billion. Ameren Missouri is unable to predict the ultimate resolution of this matter; however, such resolution could have a material adverse effect on the results of operations, financial position, and liquidity of Ameren and Ameren Missouri. In June 2022, the United States Supreme Court issued its decision in West Virginia v. EPA, clarifying that there are limits on how the EPA may regulate greenhouse gases absent further direction from the United States Congress. The court concluded that emission caps designed to shift generation from fossil-fuel-fired power plants to renewable energy facilities would require specific congressional authorization and that such authorization had not been given under the Clean Air Act. The decision by the United States Supreme Court may affect the EPA's development of any new regulations to address CO2 emissions from coal- and natural gas-fired power plants; however, at this time, Ameren Missouri cannot predict the impact of any such regulations or the decision by the United States Supreme Court on the results of operations, financial position, and liquidity of Ameren or Ameren Missouri. The IETL established emission standards that became effective in September 2021. Ameren Missouri's natural gas-fired energy centers in Illinois will be subject to limits on emissions, including CO2 and NOx, equal to their unit-specific average annual emissions from 2018 through 2020, for any rolling twelve-month period beginning October 1, 2021, through 2029. Further reductions to emissions limits will become effective between 2030 and 2040, resulting in the closure of the Venice Energy Center by 2029. The reductions could also limit the operations of Ameren Missouri's four natural gas-fired energy centers located in the state of Illinois, and will result in their closure by 2040. These energy centers are utilized to support peak loads. Subject to conditions in the IETL, these energy centers may be allowed to exceed the emissions limits in order to maintain reliability of electric utility service. Ameren and Ameren Missouri have incurred, and expect to incur, significant costs with respect to environmental compliance and site remediation. New or revised environmental regulations, enforcement initiatives, or legislation could result in a significant increase in capital expenditures and operating costs, decreased revenues, penalties or fines, reduced operations or closure of some of Ameren Missouri's coal-and natural gas-fired energy centers, which, in turn, could lead to increased liquidity and financing needs, and higher financing costs. Actions required to ensure that Ameren Missouri's facilities and operations are in compliance with environmental laws could be prohibitively expensive for Ameren Missouri if the costs are not fully recovered through rates. Environmental laws could require Ameren Missouri to close or to alter significantly the operations of its energy centers. If Ameren Missouri requests recovery of capital expenditures and costs for environmental compliance through rates, the MoPSC could deny recovery of all or a portion of these costs, prevent timely recovery, or make changes to the regulatory framework in an effort to minimize rate volatility and customer rate increases. Capital expenditures and costs to comply with future legislation or regulations might result in Ameren Missouri closing coal-fired energy centers earlier than planned. If these costs are not recoverable through base rates or other regulatory mechanisms, it could lead to an impairment of assets and reduced revenues. Any of the foregoing could have an adverse effect on our results of operations, financial positions, and liquidity.

**Current (2024):**

Our electric generation, transmission, and distribution and natural gas distribution and storage operations must comply with a variety of statutes and regulations relating to the protection of the environment and human health and safety, including permitting programs implemented by federal, state, and local authorities. Such environmental laws address air emissions; discharges to water bodies; the storage, handling and disposal of hazardous substances and waste materials; siting and land use requirements; and potential ecological impacts. Complex and lengthy processes are required to obtain and renew approvals, permits, and licenses for new, existing, or modified energy-related facilities. Additionally, the use and handling of various chemicals or hazardous materials require release prevention plans and emergency response procedures. Further, we are subject to risks from changing or conflicting interpretations of existing laws, modifications to existing laws, new laws, new or modified permit terms, and enforcement of environmental laws and permits by federal, state, and local authorities. 22 22 22 Table of Contents Table of Contents We are also subject to liability under environmental laws that address the remediation of environmental contamination on property currently or formerly owned by us or by our predecessors, as well as property contaminated by hazardous substances that we generated. Such properties include MGP sites, substations, and third-party sites, such as landfills. Additionally, individuals and non-governmental organizations may seek to enforce environmental laws against us, allege injury from exposure to hazardous materials, allege a failure to comply with environmental laws, seek to compel remediation of environmental contamination, or seek to recover damages resulting from purported contamination. Environmental regulations have a significant impact on the electric utility industry and compliance with these regulations could be costly for Ameren Missouri, which operates coal-fired power plants. As of December 31, 2023, Ameren Missouri's coal-fired energy centers represented 8% and 16% of Ameren's and Ameren Missouri's rate base, respectively. Regulations under the Clean Air Act that apply to the electric utility industry include the NSPS, the CSAPR, the MATS, and the National Ambient Air Quality Standards, which are subject to periodic review for certain pollutants. Collectively, these regulations cover a variety of pollutants, such as SO2, particulate matter, NOx, mercury, toxic metals and acid gases, and CO2 emissions. Regulations implementing the Clean Water Act govern both intake and discharges of water, as well as evaluation of the ecological and biological impact of those operations, and could require modifications to water intake structures or more stringent limitations on wastewater discharges. Depending upon the scope of modifications ultimately required by state regulators, capital expenditures associated with these modifications could be significant. The management and disposal of coal ash is regulated under the Resource Conservation and Recovery Act and the CCR Rule, which require the closure of surface impoundments at Ameren Missouri's coal-fired energy centers. The individual or combined effects of compliance with existing and new environmental regulations could result in significant capital expenditures, increased operating costs, or the closure or alteration of operations at some of Ameren Missouri's energy centers. In January 2011, the United States Department of Justice, on behalf of the EPA, filed a complaint against Ameren Missouri in the United States District Court for the Eastern District of Missouri alleging that projects performed in 2007 and 2010 at the coal-fired Rush Island Energy Center violated provisions of the Clean Air Act and Missouri law. In January 2017, the district court issued a liability ruling against Ameren Missouri and, in September 2019, entered a remedy order that required Ameren Missouri to install a flue gas desulfurization system at the Rush Island Energy Center and a dry sorbent injection system at the Labadie Energy Center. Following an appeal from Ameren Missouri, in August 2021, the United States Court of Appeals for the Eighth Circuit affirmed the liability ruling and the district court's remedy order as it related to the installation of a flue gas desulfurization system at the Rush Island Energy Center, but reversed the order as it related to the installation of a dry sorbent injection system at the Labadie Energy Center. In September 2023, the district court granted Ameren Missouri's request to modify the remedy order to allow the retirement of the Rush Island Energy Center in advance of its previously expected useful life in lieu of installing a flue gas desulfurization system. In its amended remedy order, the district court established an October 15, 2024 retirement date and, in the interim, authorized Ameren Missouri to operate the energy center as directed by the MISO. The United States Department of Justice is seeking an order from the district court providing for additional mitigation relief. Ameren Missouri could be required to implement mitigation relief measures, the costs of which could be material and which Ameren Missouri would not expect to recover. Ameren Missouri is challenging such mitigation claims, noting that the scope of any such potential additional mitigation relief should be limited by the August 2021 court of appeals decision and offset by emission reductions resulting from the accelerated retirement of the Rush Island Energy Center. The MISO designated the energy center as a system support resource in 2022 and concluded that certain reliability mitigation measures, including transmission upgrades, should occur before the energy center is retired. The Rush Island Energy Center began operating as a system support resource on September 1, 2022. In 2023, the MISO extended the system support resource designation through August 2024, and in September 2023, an agreement between Ameren Missouri and the MISO was approved by the FERC that results in the Rush Island Energy Center only operating during peak demand times and emergencies. The system support resource designation and the related agreement are subject to annual renewal and revision. Construction activities are underway for the transmission upgrades approved by the MISO, with the majority of the upgrades expected to be completed in the fall of 2024. Ameren Missouri expects to complete the last of the upgrades by mid-2025. Related to this matter, in November 2023, Ameren Missouri petitioned the MoPSC for a financing order to authorize the issuance of securitized utility tariff bonds to finance $519 million of costs related to the planned accelerated retirement of the Rush Island Energy Center, which includes the expected remaining unrecovered net plant balance associated with the facility. Ameren Missouri requested to collect the amounts necessary to repay the bonds over approximately 15 years from the date of bond issuance. In February 2024, the MoPSC staff filed a response to Ameren Missouri's petition that stated Ameren Missouri's decision to accelerate the retirement of the Rush Island Energy Center was prudent and largely supported Ameren Missouri's securitization request. However, the MoPSC staff claimed that Ameren Missouri's prior actions that resulted in the adverse ruling discussed above were imprudent and recommended that the impact of those actions on customers be considered in future rate reviews. If the remaining unrecovered net plant balance for the Rush Island Energy Center and an associated return are not recoverable through base rates or other regulatory mechanisms, Ameren Missouri would recognize an abandonment loss equal to the difference between the remaining net book value of the asset and the present value of the expected future cash flows. As of December 31, 2023, the Rush Island Energy Center had a net plant balance of $530 million included in plant to be abandoned, net, within "Property, Plant, and Equipment, Net". If Ameren Missouri is not allowed to recover Rush Island Energy Center costs through securitization or if future rate reviews result in revenue reductions based on Ameren Missouri's prior actions that resulted in the adverse ruling discussed above, it could have a material adverse effect on the results of operations, financial position, and liquidity of Ameren and Ameren Missouri. 23 23 23 Table of Contents Table of Contents In June 2022, the United States Supreme Court issued its decision in West Virginia v. EPA, clarifying that there are limits on how the EPA may regulate greenhouse gases absent further direction from the United States Congress. The court concluded that the EPA's proposed rules were designed to shift generation from fossil-fuel-fired power plants to renewable energy facilities, which was improper absent specific congressional authorization. In May 2023, the EPA issued a new proposed rule that would set CO2 emission standards for new and existing fossil-fuel-fired power plants based on the adoption of carbon capture technology, natural gas co-firing, and co-firing hydrogen fuel to reduce emissions. If the proposed rule were adopted, the affected fossil-fuel-fired power plants would be required to comply with the rule through a phased-in approach or retire. Capacity restrictions for coal-fired units could apply as early as 2030. Larger natural gas-fired power plants would be required to co-fire with hydrogen by 2032, with additional requirements by 2038. The EPA expects to issue a final rule in 2024. Legal challenges to the final rule, if adopted as proposed, are expected. Ameren and Ameren Missouri cannot predict the results of any such challenges or potential impacts of any such regulations on their results of operations, financial position, and liquidity until final regulations are adopted and the merits of such legal challenges are determined. The CEJA established emission standards that became effective in September 2021. Ameren Missouri's natural gas-fired energy centers in Illinois are subject to annual limits on emissions, including CO2 and NOx. Further reductions to emissions limits will become effective between 2030 and 2040, resulting in the closure of the Venice Energy Center by the end of 2029. The reductions could also limit the operations of Ameren Missouri's four other natural gas-fired energy centers located in the state of Illinois, and will result in their closure by 2040. These energy centers are utilized to support peak loads. Subject to conditions in the CEJA, these energy centers may be allowed to exceed the emissions limits in order to maintain reliability of electric utility service. Ameren and Ameren Missouri have incurred, and expect to incur, significant costs with respect to environmental compliance and site remediation. New or revised environmental regulations, enforcement initiatives, or legislation could result in a significant increase in capital expenditures and operating costs, decreased revenues, penalties or fines, reduced operations or closure of some of Ameren Missouri's coal-and natural gas-fired energy centers, which, in turn, could lead to increased liquidity and financing needs, and higher financing costs. Actions required to ensure that Ameren Missouri's facilities and operations are in compliance with environmental laws could be prohibitively expensive for Ameren Missouri if the costs are not fully recovered through rates. Environmental laws could require Ameren Missouri to close or to alter significantly the operations of its energy centers. If Ameren Missouri requests recovery of capital expenditures and costs for environmental compliance through rates, the MoPSC could deny recovery of all or a portion of these costs, prevent timely recovery, or make changes to the regulatory framework in an effort to minimize rate volatility and customer rate increases. Capital expenditures and costs to comply with future legislation or regulations might result in Ameren Missouri closing coal-fired energy centers earlier than planned. If these costs are not recoverable through base rates or other regulatory mechanisms, it could lead to an impairment of assets and reduced revenues. Any of the foregoing could have an adverse effect on our results of operations, financial positions, and liquidity.

---

## Modified: Ameren Missouri's ability to obtain an adequate supply of coal could limit operation of its coal-fired energy centers.

**Key changes:**

- Reworded sentence: "As of December 31, 2023, coal inventory at the Labadie Energy Center was below targeted levels and coal inventory at the Sioux Energy Center was at targeted levels."

**Prior (2023):**

Ameren Missouri owns and operates coal-fired energy centers. About 97% of Ameren Missouri's coal is purchased from the Powder River Basin in Wyoming, which has a limited number of suppliers. Deliveries from the Powder River Basin have occasionally been restricted because of rail congestion, staffing and equipment issues, infrastructure maintenance, derailments, weather, and supplier financial hardship. Coal suppliers in the Powder River Basin are experiencing financial hardship because of a decrease in demand resulting from increased natural gas use and renewable energy generation, and the impact of environmental regulations and concerns related to coal-fired generation. These financial hardships have resulted in bankruptcy filings by certain coal suppliers in recent years. As of December 31, 2022, coal inventories at the Labadie and Sioux energy centers were below targeted levels due to transportation delays in 2022. Additional delays or disruptions in the delivery of coal, failure of our coal suppliers to provide adequate quantities or quality of coal, or lack of adequate inventories of coal, including low-sulfur coal used to comply with environmental regulations, could have adverse effects on Ameren Missouri's electric generation operations. If Ameren Missouri is unable to obtain an adequate supply of coal under existing agreements, it may be required to purchase coal at higher prices or be forced to reduce generation at its coal-fired energy centers, which could adversely affect Ameren's and Ameren Missouri's results of operations, financial position, and liquidity.

**Current (2024):**

Ameren Missouri owns and operates coal-fired energy centers. About 97% of Ameren Missouri's coal is purchased from the Powder River Basin in Wyoming, which has a limited number of suppliers. Deliveries from the Powder River Basin have occasionally been restricted because of rail congestion, staffing and equipment issues, infrastructure maintenance, derailments, weather, and supplier financial hardship. As of December 31, 2023, coal inventory at the Labadie Energy Center was below targeted levels and coal inventory at the Sioux Energy Center was at targeted levels. Additional delays or disruptions in the delivery of coal, failure of our coal suppliers to provide adequate quantities or quality of coal, or lack of adequate inventories of coal, including low-sulfur coal used to comply with environmental regulations, 26 26 26 Table of Contents Table of Contents could have adverse effects on Ameren Missouri's electric generation operations. If Ameren Missouri is unable to obtain an adequate supply of coal under existing agreements, it may be required to purchase coal at higher prices or be forced to reduce generation at its coal-fired energy centers, which could adversely affect Ameren's and Ameren Missouri's results of operations, financial position, and liquidity.

---

## Modified: The construction and acquisition of, and capital improvements to, electric and natural gas utility infrastructure, along with Ameren Missouri's ability to implement its Smart Energy Plan, which is aligned with its 2023 IRP, involve substantial risks.

**Key changes:**

- Reworded sentence: "We estimate that we will invest up to $22.8 billion (Ameren Missouri - up to $13.5 billion; Ameren Illinois - up to $7.6 billion; ATXI - up to $1.7 billion) of capital expenditures from 2024 through 2028."
- Reworded sentence: "Our ability to complete construction projects successfully within projected estimates, including schedule, performance, and/or cost, and to implement Ameren Missouri's Smart Energy Plan, which may include acquisition of generation facilities after they are constructed, is contingent upon many factors and subject to substantial risks."

**Prior (2023):**

We expect to make significant capital expenditures to maintain and improve our electric and natural gas utility infrastructure and to comply with existing environmental regulations. We estimate that we will invest up to $20.5 billion (Ameren Missouri - up to $10.8 billion; Ameren Illinois - up to $9.5 billion; ATXI - up to $0.2 billion) of capital expenditures from 2023 through 2027. For additional information on these estimates, see Liquidity and Capital Resources - Capital Expenditures in Management's Discussion and Analysis of Financial Condition and Results of Operations under Part II, Item 7, of this report. Investments in Ameren's rate-regulated operations are expected to be recoverable from customers, but they are subject to prudence reviews and are exposed to regulatory lag of varying degrees by jurisdiction. 25 25 25 Table of Contents Table of Contents Our ability to complete construction projects successfully within projected estimates, including schedule, performance, and/or cost, and to implement Ameren Missouri's Smart Energy Plan, which may include acquisition of generation facilities after they are constructed, is contingent upon many factors and subject to substantial risks. These factors include, but are not limited to, the following: project management expertise; escalating costs and/or shortages for labor, materials, and equipment, including changes to tariffs on materials or government actions; the ability of suppliers, contractors, and developers to meet contractual commitments and timely complete projects; changes in the scope and timing of projects; the ability to obtain required regulatory, project, and permit approvals; the ability to obtain necessary rights-of-way, easements, and transmission connections at an acceptable cost in a timely fashion; unsatisfactory performance by the projects when completed; the inability to earn an adequate return on invested capital; the ability to raise capital on reasonable terms; and other events beyond our control, including construction delays due to weather. With respect to the transition of Ameren Missouri's generation fleet and carbon emission reduction targets outlined in the 2022 Change to the 2020 IRP, factors also include MoPSC approval for the retirement of energy centers and new or continued customer energy-efficiency programs; the ability to enter into build-transfer agreements for renewable generation and acquire that generation at a reasonable cost; levels of customer participation in the energy-efficiency programs; the cost and commercial availability of wind, solar, and other renewable generation and battery storage technologies; the cost of natural gas or hydrogen CT technologies; the ability to qualify for, and use or transfer, federal production or investment tax credits; changes in environmental laws or requirements, including those related to CO2 and other greenhouse gas emissions; and energy prices and demand. In addition, government investigations relating to the importation of solar panel components could affect the cost and the availability of solar panel components. Any of these risks could result in higher costs, the inability to complete anticipated projects, or facility closures, and could adversely affect our results of operations, financial position, and liquidity.

**Current (2024):**

We expect to make significant capital expenditures to maintain and improve our electric and natural gas utility infrastructure and to comply with existing environmental regulations. We estimate that we will invest up to $22.8 billion (Ameren Missouri - up to $13.5 billion; Ameren Illinois - up to $7.6 billion; ATXI - up to $1.7 billion) of capital expenditures from 2024 through 2028. For additional information on these estimates, see Liquidity and Capital Resources - Capital Expenditures in Management's Discussion and Analysis of Financial Condition and Results of Operations under Part II, Item 7, of this report. Investments in Ameren's rate-regulated operations are expected to be recoverable from customers, but they are subject to prudence reviews and are exposed to regulatory lag of varying degrees by jurisdiction. Our ability to complete construction projects successfully within projected estimates, including schedule, performance, and/or cost, and to implement Ameren Missouri's Smart Energy Plan, which may include acquisition of generation facilities after they are constructed, is contingent upon many factors and subject to substantial risks. These factors include, but are not limited to, the following: project management expertise; the ability of suppliers, contractors, and developers to meet contractual commitments and timely complete projects, which is dependent upon the availability of necessary labor, materials, and equipment; escalating costs, including but not limited to changes to tariffs on materials or government actions; changes in the scope and timing of projects; the ability to obtain required regulatory, project, and permit approvals; the ability to obtain necessary rights-of-way, easements, and transmission connection agreements at an acceptable cost in a timely fashion; unsatisfactory performance by the projects when completed; the inability to earn an adequate return on invested capital; the ability to raise capital on reasonable terms; geopolitical conflict and other events beyond our control, including construction delays due to weather. With respect to the transition of Ameren Missouri's generation fleet and carbon emission reduction targets outlined in the 2023 IRP, factors also include Ameren Missouri's ability to obtain CCNs from the MoPSC, and any other required approvals for the addition of renewable resources or natural gas-fired generation, retirement of energy centers, and new or continued customer energy-efficiency 25 25 25 Table of Contents Table of Contents programs; the ability to enter into agreements for renewable or natural gas-fired generation and acquire or construct that generation at a reasonable cost; the ability to obtain NRC approval for an extension of the operating license for the Callaway Energy Center beyond its current 2044 expiration date; the ability to qualify for, and use or transfer, federal production or investment tax credits; the cost of wind, solar, and other renewable generation and battery storage technologies; the cost of natural gas or hydrogen CT technologies; the ability to maintain system reliability during and after the transition to clean energy generation; new and/or changes in environmental regulations, including those related to CO2 and other greenhouse gas emissions; energy prices and demand. Any of these risks could result in higher costs, the inability to complete anticipated projects, or facility closures, and could adversely affect our results of operations, financial position, and liquidity.

---

## Modified: We are subject to employee workforce factors that could adversely affect our operations.

**Key changes:**

- Reworded sentence: "As of December 31, 2023, approximately 23% of Ameren's, Ameren Missouri's, and Ameren Illinois' total employees were 55 years old or older."

**Prior (2023):**

Our businesses depend upon our ability to employ and retain key officers and other skilled professional and technical employees. Certain specialized knowledge that focuses on skilled-craft and STEM-related disciplines is required to construct and operate generation, transmission, and distribution assets. Further, a significant portion of our work force is nearing retirement. As of December 31, 2022, approximately 25%, 25%, and 23% of Ameren's, Ameren Missouri's, and Ameren Illinois' total employees were 55 years old or older, respectively. We are also party to collective bargaining agreements that collectively represent about 47%, 59%, and 55% of Ameren's, Ameren Missouri's and Ameren Illinois' total employees, respectively. The Ameren Missouri collective bargaining unit contracts expire in 2025 and 2026, which cover 4% and 96% of represented employees, respectively. The Ameren Illinois collective bargaining unit contracts expire in 2023 and 2026, which cover 8% and 92% of represented employees, respectively. Remote working arrangements could increase our data security risks, including loss of data related to sensitive customer, employee, financial, and operating system information, through insider or outsider actions. Certain events, such as significant delays in finding appropriate replacement talent, inadequately trained replacement employees, a mismatch of skill sets to future needs, any work stoppage experienced in connection with negotiations of collective bargaining agreements, or challenges with remote working arrangements, could adversely affect our operations.

**Current (2024):**

Our businesses depend upon our ability to employ and retain key officers and other skilled professional and technical employees. Certain specialized knowledge that focuses on skilled-craft and STEM-related disciplines is required to construct and operate generation, transmission, and distribution assets. Further, a significant portion of our work force is nearing retirement. As of December 31, 2023, approximately 23% of Ameren's, Ameren Missouri's, and Ameren Illinois' total employees were 55 years old or older. We are also party to collective bargaining agreements that collectively represent about 46%, 58%, and 54% of Ameren's, Ameren Missouri's and Ameren Illinois' total employees, respectively. The Ameren Missouri collective bargaining unit contracts expire in 2025 and 2026, and cover 4% and 96% of represented employees, respectively. The Ameren Illinois collective bargaining unit contracts expire in 2026 and 2027, and cover 92% and 8% of represented employees, respectively. Remote working arrangements could increase our data security risks, including loss of data 29 29 29 Table of Contents Table of Contents related to sensitive customer, employee, financial, and operating system information, through insider or outsider actions. Certain events, such as significant delays in finding appropriate replacement talent, inadequately trained replacement employees, a mismatch of skill sets to future needs, any work stoppage experienced in connection with negotiations of collective bargaining agreements, or challenges with remote working arrangements, could adversely affect our operations.

---

## Modified: The electric and natural gas rates that we are allowed to charge are determined through regulatory proceedings, which are subject to intervention and appeal. Rates are also subject to legislative actions, which are largely outside of our control. Certain events could prevent us from recovering our costs in a timely manner or at all, or from earning adequate returns on our investments.

**Key changes:**

- Reworded sentence: "Ameren Missouri's electric and natural gas utility rates established in those proceedings 20 20 20 Table of Contents Table of Contents are primarily based on historical costs, revenues, and sales volumes."
- Removed sentence: "Ameren Illinois is utilizing the IEIMA performance-based formula ratemaking framework to establish annual customer rates effective through 2023."
- Removed sentence: "Effective for rates beginning in 2024 through at least 2027, Ameren Illinois will establish electric distribution rates through an MYRP, which is subject to a reconciliation cap and includes an ROE determined by the ICC applicable to each year of the four-year period."
- Removed sentence: "As a result of its participation in the IEIMA performance-based formula ratemaking, Ameren Illinois' ROE for its electric distribution service through 2023 and its electric energy-efficiency investments are directly correlated to yields on United States Treasury bonds."
- Removed sentence: "Additionally, Ameren Illinois is subject to certain performance standards."

**Prior (2023):**

The rates that we are allowed to charge for our utility services significantly influence our results of operations, financial position, and liquidity. The electric and natural gas utility industry is highly regulated. The utility rates charged to customers are determined by governmental entities, including the MoPSC, the ICC, and the FERC. Decisions by these entities are influenced by many factors, including the cost of providing service, the prudency of expenditures, the quality of service, regulatory staff knowledge and experience, customer intervention, and economic conditions, as well as social and political views. Decisions made by these governmental entities regarding customer rates are largely outside of our control. We are exposed to regulatory lag, including the impact of inflationary pressures, and cost disallowances to varying degrees by jurisdiction, which, if unmitigated, could adversely affect our results of operations, financial position, and liquidity. Rate orders are also subject to appeal, which creates additional uncertainty as to the rates that we will ultimately be allowed to charge for our services. From time to time, our regulators may approve trackers, riders, or other recovery mechanisms that allow electric or natural gas rates to be adjusted without a traditional regulatory rate review. These mechanisms could be changed or terminated. Ameren Missouri's electric and natural gas utility rates and Ameren Illinois' natural gas utility rates are typically established in regulatory proceedings that take up to 11 months to complete. Ameren Missouri's electric and natural gas utility rates established in those proceedings are primarily based on historical costs, revenues, and sales volumes. Ameren Illinois' natural gas rates established in those proceedings are 20 20 20 Table of Contents Table of Contents based on estimated future costs, revenues, and sales volumes. Beginning in 2024 through at least 2027, Ameren Illinois' electric distribution rates will be established through an MYRP as discussed in the following risk factor, which will be based on estimated future costs and an applicable revenue requirement reconciliation, which may not allow for full recovery of actual costs due to a reconciliation cap. Thus, the rates that we are allowed to charge for utility services may not match our actual costs at any given time. Rates include an allowed return on investments established by the regulator, including a return at the applicable WACC on rate base, and an amount for income taxes based on the currently applicable statutory income tax rates and amortization associated with excess deferred income taxes. Although rate regulation is premised on providing an opportunity to earn a reasonable rate of return on rate base, there can be no assurance that the regulator will determine that our costs were prudently incurred or that the regulatory process will result in rates that will produce full recovery of such costs or provide for an opportunity to earn a reasonable return on those investments. Ameren Missouri and Ameren Illinois, and the utility industry generally, have an increased need for cost recovery, primarily driven by capital investments, which is likely to continue in the future. The resulting increase to the revenue requirement needed to recover such costs and earn a return on investments could result in more frequent regulatory rate reviews and requests for cost recovery mechanisms. Additionally, increasing rates could result in regulatory or legislative actions, as well as competitive or political pressures, all of which could adversely affect our results of operations, financial position, and liquidity. Ameren Illinois is utilizing the IEIMA performance-based formula ratemaking framework to establish annual customer rates effective through 2023. Effective for rates beginning in 2024 through at least 2027, Ameren Illinois will establish electric distribution rates through an MYRP, which is subject to a reconciliation cap and includes an ROE determined by the ICC applicable to each year of the four-year period. As a result of its participation in the IEIMA performance-based formula ratemaking, Ameren Illinois' ROE for its electric distribution service through 2023 and its electric energy-efficiency investments are directly correlated to yields on United States Treasury bonds. Additionally, Ameren Illinois is subject to certain performance standards. Ameren Illinois is utilizing the IEIMA performance-based formula ratemaking framework to establish annual customer rates effective through 2023 and will reconcile the related revenue requirements through an IEIMA reconciliation. The IETL resulted in changes to the regulatory framework applicable to Ameren Illinois' electric distribution business by giving Ameren Illinois the option to file an MYRP with the ICC by mid-January 2023, with rates effective beginning in 2024, or establish future rates through a traditional regulatory rate review, among other things. An MYRP would establish rates for a four-year period, and Ameren Illinois has the option to file for an MYRP every four years. Ameren Illinois elected to file an MYRP in January 2023 for rates effective in 2024 through 2027 with the ICC. The MYRP also allows Ameren Illinois to reconcile its actual revenue requirement, as adjusted for certain cost variations, to ICC-approved electric distribution service rates on an annual basis, subject to a reconciliation cap. The reconciliation cap limits the annual adjustment to 105% of the annual revenue requirement approved by the ICC. Certain variations from forecasted costs would be excluded from the reconciliation cap, including those associated with major storms; new business and facility relocations; changes in the timing of certain expenditures or investments into or out of the applicable calendar year; and changes in interest rates, income taxes, taxes other than income taxes, pension and other post-retirement benefits costs, and amortization of certain assets. The reconciliation cap also excludes costs recovered through riders outside of base rates, such as riders for electric energy-efficiency investments, power procurement and transmission services, renewable energy credit compliance, zero emission credits, certain environmental costs, and bad debt write-offs, among others. Ameren Illinois' existing riders will remain effective and electric distribution service revenues will continue to be decoupled from sales volumes under the MYRP. The actual revenue requirement for a particular year would incorporate Ameren Illinois' year-end rate base and actual capital structure for such year, provided that the common equity ratio in such capital structure may not exceed that approved by the ICC in the MYRP. In addition, the ICC will determine the ROE applicable to each year of the four-year period. Changes in economic conditions could result in the predetermined ROE becoming inadequate over the four-year period. By law, Ameren Illinois' electric distribution revenues are decoupled from sales volumes regardless of the process used to establish electric distribution rates, which ensures that the electric distribution revenues authorized in a regulatory rate review are not affected by changes in sales volumes. Ameren Illinois' electric energy-efficiency program rider, which includes a return at the applicable WACC on its program investments, is subject to performance-based formula ratemaking. The ICC annually reviews each Ameren Illinois rate filing for reasonableness and prudency. If the ICC were to conclude that Ameren Illinois' costs were not prudently incurred, the ICC would disallow recovery of such costs. The allowed ROE under the IEIMA and electric energy-efficiency formula ratemaking recovery mechanisms is based on the annual average of the monthly yields of the 30-year United States Treasury bonds plus 580 basis points. Therefore, Ameren Illinois' annual ROE for its electric distribution business is directly correlated to the yields on such bonds, which are outside of Ameren Illinois' control. A 50 basis point change in the annual average of the monthly yields of the 30-year United States Treasury bonds would result in an estimated $12 million change in Ameren's and Ameren Illinois' annual net income, based on Ameren Illinois' 2023 projected year-end rate base, including electric energy-efficiency investments. Ameren Illinois' electric distribution business is also subject to performance standards. Failure to achieve the standards would result in a reduction in the company's allowed ROE calculated under the formula ratemaking recovery mechanisms. The performance standards applicable to electric distribution service under the IEIMA include improvements in service reliability to reduce both the frequency and duration of outages, a reduction in the number of estimated bills, a reduction of consumption from inactive meters, and a reduction in bad 21 21 21 Table of Contents Table of Contents debt expense. The 2023 allowed ROE for electric distribution service is subject to the performance standards related to reduced estimated bills and bad debt expense, and may be decreased for penalties up to 10 basis points if these performance standards are not met. The allowed ROE on energy-efficiency investments can be increased or decreased up to 200 basis points, depending on the achievement of annual energy savings goals. Any adjustments to the allowed ROE for energy-efficiency investments will depend on annual performance for a historical period relative to energy savings goals. In 2022, 2021, and 2020, there were no performance-related basis point adjustments that materially affected financial results. With respect to the MYRP, a September 2022 ICC order approved total ROE incentives and penalties of 24 basis points, allocated among the seven performance metrics. These performance metrics include improvements in service reliability in both the frequency and duration of outages, a reduction in peak loads, an increased percentage of spend with diverse suppliers, a reduction in disconnections for certain customers, and improved timeliness in response to customer requests for interconnection of distributed energy resources. These performance metrics and the ROE incentives and penalties will apply annually from 2024 through 2027 under the MYRP filed by Ameren Illinois. While the ICC has approved a plan for Ameren Illinois to invest approximately $120 million per year in electric energy-efficiency programs through 2025, the ICC has the ability to reduce the amount of electric energy-efficiency savings goals in the future plan program years if there are insufficient cost-effective programs available, which could reduce the investments in electric energy-efficiency programs.

**Current (2024):**

The rates that we are allowed to charge for our utility services significantly influence our results of operations, financial position, and liquidity. The electric and natural gas utility industry is highly regulated. The utility rates charged to customers are determined by governmental entities, including the MoPSC, the ICC, and the FERC. Decisions by these entities are influenced by many factors, including the cost of providing service, the prudency of expenditures, the quality of service, regulatory staff knowledge and experience, customer intervention, and economic conditions, as well as social and political views. Decisions made by these governmental entities regarding customer rates are largely outside of our control. We are exposed to regulatory lag, including the impact of inflationary pressures, and cost disallowances to varying degrees by jurisdiction, which, if unmitigated, could adversely affect our results of operations, financial position, and liquidity. Rate orders are also subject to appeal, which creates additional uncertainty as to the rates that we will ultimately be allowed to charge for our services. From time to time, our regulators may approve trackers, riders, or other recovery mechanisms that allow electric or natural gas rates to be adjusted without a traditional regulatory rate review. These mechanisms could be changed or terminated. Ameren Missouri's electric and natural gas utility rates and Ameren Illinois' natural gas utility rates are typically established in regulatory proceedings that take up to 11 months to complete. Ameren Missouri's electric and natural gas utility rates established in those proceedings 20 20 20 Table of Contents Table of Contents are primarily based on historical costs, revenues, and sales volumes. Ameren Illinois' natural gas rates established in those proceedings are based on estimated future costs, revenues, and sales volumes. Effective for rates beginning in 2024 through at least 2027, Ameren Illinois' electric distribution rates will be established through an MYRP as discussed in the following risk factor. An MYRP includes a revenue requirement reconciliation, which may not allow for full recovery of actual costs due to a reconciliation cap. Thus, the rates that we are allowed to charge for utility services may not match our actual costs at any given time. Rates include an allowed return on investments established by the regulator, including a return at the applicable WACC on rate base, and an amount for income taxes based on the currently applicable statutory income tax rates and amortization associated with excess deferred income taxes. Although rate regulation is premised on providing an opportunity to earn a reasonable rate of return on rate base, there can be no assurance that the regulator will determine that our costs were prudently incurred or that the regulatory process will result in rates that will produce full recovery of such costs or provide for an opportunity to earn a reasonable return on those investments. Ameren Missouri and Ameren Illinois, and the utility industry generally, have an increased need for cost recovery, primarily driven by capital investments, which is likely to continue in the future. The resulting increase to the revenue requirement needed to recover such costs and earn a return on investments could result in more frequent regulatory rate reviews and requests for cost recovery mechanisms. Additionally, increasing rates could result in regulatory or legislative actions, as well as competitive or political pressures, all of which could adversely affect our results of operations, financial position, and liquidity.

---

## Modified: As a result of the election to use the PISA, effective in 2024, Ameren Missouri's electric service business is subject to a limitation on increasing the annual revenue requirement due to the inclusion of incremental PISA deferrals in the revenue requirement.

**Key changes:**

- Reworded sentence: "Pursuant to a Missouri law that became effective in August 2022, Ameren Missouri's PISA election was extended through December 2028 and an additional extension through December 2033 is allowed if requested by Ameren Missouri and approved by the MoPSC, among other things."

**Prior (2023):**

Ameren Missouri's rate cap under the PISA is effective through 2023 and limits electric service rate increases to a 2.85% compound annual growth rate in the average overall customer rate per kilowatthour, based on the electric rates that became effective in April 2017, less half of the annual savings from the TCJA that was passed on to customers as approved in a July 2018 MoPSC order. Increased capital investments and operating costs could cause customer rates to exceed the 2.85% rate cap effective through 2023. In addition, a decrease in off-system sales or capacity revenues or an increase in purchased power expense, all of which are included in net energy costs within the FAC, could also contribute to customer rates exceeding the rate cap. Off-system sales are affected by generation availability, which is affected by planned and unplanned outages at Ameren Missouri's energy centers, curtailment of generation resulting from unfavorable economic conditions, the addition of new generation sources, and retirements of Ameren Missouri's energy centers, among other things. If rate changes from the FAC or the RESRAM riders would cause rates to temporarily exceed the 2.85% rate cap, the overage would be deferred for future recovery in the next regulatory rate review; however, rates established in such regulatory rate review would be subject to the rate cap. Any deferred overages approved for recovery would be recovered over a period of 20 years following approval of amounts in a regulatory rate review. Excluding customer rates under the MEEIA rider, which are not subject to the rate cap, Ameren Missouri would incur a penalty equal to the amount of deferred overage that would cause customer rates to exceed the 2.85% rate cap until new rates are established in the next regulatory rate review. A penalty incurred as the result of exceeding the rate cap could adversely affect Ameren's and Ameren Missouri's results of operations, financial position, and liquidity. Also, due to a change in customer behavior and certain business practices resulting from the COVID-19 pandemic, there has been a shift in sales volumes by customer class at Ameren Missouri, which began in 2020, resulting in an increase in residential sales, and a decrease in commercial and industrial sales. While Ameren Missouri's electric sales volumes in 2022, excluding the estimated effects of weather and customer energy-efficiency programs, were comparable to the same period in 2021 and to pre-pandemic levels, long-term declines in sales volumes, along with increased capital investments and operating costs, could result in Ameren Missouri's inability to recover amounts exceeding the rate cap. Missouri Senate Bill 745 became effective on August 28, 2022. The law extended Ameren Missouri's PISA election through December 2028 and allows for an additional extension through December 2033 if requested by Ameren Missouri and approved by the MoPSC, among other things. The law established a 2.5% annual limit on increases to the electric service revenue requirement used to set customer rates due to the inclusion of incremental PISA deferrals in the revenue requirement. The limitation will be effective for revenue requirements approved 22 22 22 Table of Contents Table of Contents by the MoPSC after January 1, 2024, and will be based on the revenue requirement established in the immediately preceding rate order. Increased capital expenditures could cause incremental PISA deferrals to exceed the 2.5% limitation when it is effective, and such amounts exceeding the 2.5% limitation would be excluded from recovery under future revenue requirements. Failure to align capital investments under the 2.5% limitation could adversely affect Ameren's and Ameren Missouri's results of operations, financial position, and liquidity.

**Current (2024):**

Pursuant to a Missouri law that became effective in August 2022, Ameren Missouri's PISA election was extended through December 2028 and an additional extension through December 2033 is allowed if requested by Ameren Missouri and approved by the MoPSC, among other things. This law also established a 2.5% annual limit on increases to the electric service revenue requirement used to set customer rates, compared to the revenue requirement established in the immediately preceding rate order, due to the inclusion of incremental PISA deferrals in the revenue requirement. The limitation will be effective for revenue requirements approved by the MoPSC after January 1, 2024. Increased capital expenditures could cause incremental PISA deferrals to exceed the 2.5% limitation, and such amounts exceeding the 2.5% limitation would be excluded from recovery under future revenue requirements. Failure to limit capital investments to an amount which maintains PISA deferrals under the 2.5% limitation could adversely affect Ameren's and Ameren Missouri's results of operations, financial position, and liquidity.

---

## Modified: Ameren Illinois' QIP expired in December 2023, which will subject Ameren Illinois to increased regulatory lag with respect to certain natural gas infrastructure investments. In addition, reconciliation hearings to determine the accuracy and prudence of natural gas capital investments recovered under the QIP are still ongoing.

**Key changes:**

- Reworded sentence: "The QIP expired in December 2023."

**Prior (2023):**

The QIP provides Ameren Illinois with recovery of, and a return on, qualifying natural gas infrastructure investments that are placed in service between regulatory rate reviews. Infrastructure investments under the QIP earn a return at the applicable WACC. Ameren Illinois' QIP is subject to a rate impact limitation of a cumulative 4% per year since the most recent delivery service rate order, with no single year exceeding 5.5%. If the rate impact limitation was met in a particular year, the amount of rate base causing the QIP rate to exceed the limitation would be exposed to regulatory lag until a year when that amount could be recovered under QIP or is added to rate base as a part of a regulatory rate review. Upon issuance of a natural gas delivery service rate order, QIP rate base is transferred to base rates and the QIP is reset to zero. Without legislative action, the QIP will expire after December 2023. If Ameren Illinois is unable to recover investments under the QIP or there is no other regulatory change, Ameren Illinois will be subject to increased regulatory lag on its natural gas infrastructure investments that are placed in service between regulatory rate reviews, which could adversely affect Ameren's and Ameren Illinois' investment plans and results of operations, financial position, and liquidity.

**Current (2024):**

The QIP expired in December 2023. Previously, it provided Ameren Illinois with recovery of, and a return on, qualifying natural gas infrastructure investments that were placed in service between regulatory rate reviews. Infrastructure investments under the QIP earned a return at the applicable WACC. As a result of the expiration of the QIP, Ameren Illinois is subject to increased regulatory lag on its natural gas infrastructure investments that are placed in service between regulatory rate reviews, which could adversely affect Ameren's and Ameren Illinois' investment plans and results of operations, financial position, and liquidity. In addition, reconciliation hearings to determine the accuracy and prudence of natural gas capital investments recovered under the QIP from 2020 to 2023 are still ongoing. In October 2023, the Illinois Attorney General's office challenged the recovery of capital investments that were made during 2020, alleging that the ICC should disallow approximately $53 million in natural gas capital investments as improper and imprudent, providing a potential over-recovery of approximately $3 million in 2020. In October 2023, the ICC staff filed testimony that supports the prudence and reasonableness of the capital investments made during 2020. Ameren Illinois' 2020 QIP rate recovery request under review by the ICC was within the rate increase limitations allowed by law. The ICC is under no deadline to issue an order in this proceeding. Ameren Illinois cannot predict the ultimate outcome of this regulatory proceeding.

---